Towers Installed

September 2022

On September 13 a team from Doppelmayr and HeliCarrier Helicopters were on site to assist in the aerial placement of the Seven Brother Express Quad towers. The team worked quickly placing 13 towers on the already cured concrete foundations.

Each tower took 2 flights to install, one for the tower structure and one for the cross arm. Starting at the top of the lift line the crew worked methodically down the mountain. A total of 26 flights were made for all towers to be completed. The last tower at the bottom terminal will be installed by crane at a later date.

All work will be completed in time for the opening day of the 2022/23 season!